Scaffolding a shop or clinic while it stays open

21 July 2026 | Scaffolders in South Wales

Scaffolding above a high street shop front
Photo: Jaggery, CC BY-SA 2.0, via Wikimedia Commons.

Yes, most shops and clinics can stay open with a scaffold up, as long as it’s planned around the way customers reach the door and not just around the building. The design of the scaffold is the easy part. What makes or breaks these jobs is timing, protection over the entrance, and being honest with customers about what’s going on.

Different premises, different problems

A shop and a clinic can share a street and have nothing in common once a scaffold goes up.

Think about an independent such as The Curious Hideaway, on West Street in Weston-super-Mare, stocked with the work of many small makers. A shop like that depends on people seeing the window and wandering in. Hide the frontage behind boards and sheeting for six weeks, and passing trade is what suffers first. So the questions are about visibility, signage and keeping the pavement inviting.

A clinic works differently. At a practice such as Unique Clinic Bristol, where Saturday hours are by appointment, people come at a set time, often having travelled specially, and they’re expecting a calm, private room. Passing trade doesn’t come into it. What matters is that they can find the door, that noisy work doesn’t land on top of a booked session, and that nobody is standing outside a first-floor treatment room window. Those are the two ends of a spectrum, and your premises will sit somewhere on it.

Start with who is responsible

A business having work done on its own premises is a commercial client under the CDM 2015 regulations, and HSE says that brings the full set of client duties, even on a small job. That includes making suitable arrangements for managing the project, appointing designers and contractors with the right skills, allowing enough time and resources, and providing information to them. You don’t need to become an expert, but you do need to tell the people doing the work what they need to know about your building and how you use it.

If you rent, read your lease and speak to the landlord early. Find out who’s commissioning the work and whether they’ve thought about the business underneath it. It’s your customers who will be walking under it either way.

What to work out before a tube goes up

Entrances and fire exits

Walk every route with your scaffolder: customer door, staff door, deliveries, bins and fire exits. Standards and braces must not block a fire route, and neither must any fencing put up to keep people off the scaffold. HSE is specific about that last point in its alert on scaffold security.

Protection overhead

HSE’s guidance on protecting the public says objects must not be able to fall outside the site boundary. On a scaffold, that means options like toe boards, brick guards and netting, with fans or covered walkways where needed. Over a shop door you’d expect to discuss a covered route, so customers aren’t walking directly beneath the work. HSE lists protection fans and pavement gantries among the structures that normally need a design, though TG20:21 covers a limited range of fans. Tell your scaffolder early, because it affects the plan and the time needed.

The pavement

If the scaffold encroaches on the highway, including the pavement, HSE says it needs a licence from the highway authority under section 169 of the Highways Act 1980. Councils vary on the detail. Newport says you must have the licence before erecting anything, and asks for a site plan, an elevation and details of any public safety measures. Cardiff’s terms say that scaffolding in the city centre and on principal routes is to be put up and taken down on a Sunday unless the council agrees otherwise, which can work out well for a business that closes that day. Always check the current conditions for your own street, and agree in writing who applies.

Erecting and dismantling

HSE’s position is that scaffolds should never be put up or taken down over people or busy pavements. It should happen in a segregated area during quieter periods, and a footpath or road closure may be needed if the work endangers the public. So there’s a good chance these days won’t be normal trading days. Plan for that. Early mornings, a closed day or a Sunday may all be options, depending on the licence.

Disabled access

A scaffold and a narrowed pavement can make a step-free route disappear. Under the Equality Act 2010 the duty on service providers to make reasonable adjustments is anticipatory, so you shouldn’t wait for a disabled customer to ask. Citizens Advice gives a temporary ramp as an example of an adjustment. Check the route with a wheelchair or pushchair in mind, keep it clear of materials, and take advice if you’re unsure what’s reasonable in your situation.

Keeping customers coming

  • Say you’re open, in big letters. A banner on the scaffold or a sign at pavement level is a simple fix. Ask first where it can be fixed: signs and banners add wind load, and advertising banners are on HSE’s list of items normally needing a design.
  • Warn people in advance. Put it on your website, social media and appointment confirmations, with directions if the door has changed.
  • Keep the window usable. Ask if sheeting can be left off at street level, and whether netting will do on the lifts above. Any sheeting or netting has to be cleared with those designing and erecting the scaffold first.
  • Look at the noisy days. Ask the contractor for notice of disruptive tasks, so an appointment book can be arranged around them.
  • Protect privacy. For upper-floor rooms used by clients, sort out blinds or frosted film before anyone’s working outside them.
  • Lock it down at night. Removing or securing the bottom ladder out of hours deals with both trespass and burglary risk. Tell your own insurer about the works too.

Who to talk to and when

Bring in the scaffolder as early as you bring in the builder. Share your busiest days, your delivery times and any events in the calendar. That gives everyone a chance to plan around them. We look at a lot of this at survey stage for commercial scaffolding, and it’s easier to fix on paper than on a Saturday morning with customers waiting outside.

If you’ve got work coming up and you need to keep the doors open, tell us about the premises and we’ll give you a straight answer on what’s practical.

Free, no obligation

Get a scaffolding quote

Tell us where the job is and what you need to reach. If you would rather talk it through, call us.